Hearts of Oak: Work progressing sturdily on Pobiman project

Share this with Email Share this with Facebook Share this with Twitter Share this with Whatsapp

A visit by the Hearts Communication team to the site of the much talked about project clearly showed that much work has been done on the site and, it should be ready enough in time for the prefabricated structures to be fixed.

Advertisement

The local contractor began work on Friday, June 3, 2020, as they are preparing the groundwork to put it into shape before the main contractor Prefabex Yapi Teknolojiller San Ve Tic Limited of Turkey takes over.

Prefabex is building the structures in Turkey and the local contractors have been tasked for the foundation under the Turkish company's supervision.

Turkish construction firm Prefabex Yapi Teknolojiller San Ve Tic Limited are the main contractors for the project and are supervising the work of the local contractors.

When completed, the Pobiman Project will have a Staff Residence, Senior Housing Unit, Gym, Training Centres (Pitches), Laundry, Swimming Pool, Lockers, Toilet Facilities, Kitchen and Dining Hall.

The Hearts of Oak Board headed by Togbe Afede XIV is committed to making the club the preeminent one and a

point of reference to emulate in Africa, and the Pobiman Academy Project is viewed in this direction as a standard marker.

Below is a picture from the construction site

Advertisement

 

 

Source: Hearts Media